15.12.2018

Start of construction! October–November

Building №1

  • The existing base under the building base was dismantled;
  • works on the device of the sheet piling;
  • the foundation pit of the building was dug under 1 and 2 sections of the building by 100% under section No. 3 by 60%;
  • the existing piles of the first bush of injection piles were tested;
  • work has begun on arranging the building's brown injection piles.

Building №2

  • The existing base under the base of the building was dismantled;
  • works on the device of the sheet piling.
/