15 February 2019

Construction progress, December-January 2019

House #1

  • Arrangement of pile fields Sections №1 done
  • Arrangement of pile fields Sections №2 done
  • Arrangement of horizontal insulation raft Sections №2 done
  • Tower crane №1 was installed
  • TD was received for electricity supply, water, sewage and radio engineering

Now, the rafting section of Section №2 has been completed and works are being carried out on:

  • Installation of base for grillage Section №1
  • Horizontal insulation of rigging arrangement of Section №1
  • Installation of a monolithic frame of walls of a technical underground Section №2
  • Arrangement  for pile field Section №3

Detailed video review on the YouTube channel.