15 February 2019

Construction progress, December – January 2019

Building №1

  • Arrangement of pile fields Sections 1 done;
  • arrangement of pile fields Sections 2 done;
  • arrangement of horizontal insulation raft Sections 2 done;
  • tower crane №1 was installed;
  • TD was received for electricity supply, water, sewage and radio engineering.

Now, the rafting section of Section 2 has been completed and works are being carried out on:

  • Installation of base for grillage Section 1;
  • Horizontal insulation of rigging arrangement of Section 1;
  • Installation of a monolithic frame of walls of a technical underground Section 2;
  • Arrangement  for pile field Section 3.