15.03.2019

Construction progress, February 2019

Building №1
Section 1

  • installation of the basis footing;
  • installation for horizontal insulation with bentonite mats;
  • grillage installation (reinforcement concreting) 1048 m3.

Section 2

  • installation of vertical elements of walls, pylons of a technical underground;
  • installation of overlapping plate of a technical underground;
  • installation of walls' vertical elements, pylons of the 1st floor (50%).

Section 3

  • installation of the pile field (40%).

Building №2

  • the dismantling of the plate of the existing grillage in the building spot was completed.

Detailed video review on the YouTube channel.

/